From enquiry to installation
Sixteen stages, each with defined inputs, hold points and records. We fabricate to your approved drawings and deliver steel your erector can install. Use this path to plan your submittals, inspections and site work.
RFQ and scope review
We review your RFQ package before pricing: drawings, specification, governing codes, material grades, coating system, inspection requirements, delivery terms and site constraints.
- Request for information (RFI) log for gaps, conflicts and assumptions
- Review of the specification, drawings, bill of quantities and bid documents
- Confirmation of governing codes, for example AWS D1.1, ASME Section IX, EN ISO 15614 or CSA W59, as specified
- Identification of special requirements: heavy sections, stainless steel, galvanizing, fire protection, third-party witness
You receive: RFI log and a confirmed scope summary
Quotation and commercial terms
A priced proposal that states what is included, what is excluded and the assumptions behind both, so there is no ambiguity at award.
- Itemized price by tonnage and scope, with unit rates for changes
- Inclusions, exclusions, clarifications and any deviations from the specification
- Lead time and a preliminary fabrication and shipping schedule
- Payment milestones, Incoterms (for example FOB, CIF or DAP), validity, warranty and change-order terms
You receive: Priced proposal and preliminary schedule
Purchase order, kick-off and quality plan sign-off
On award of a purchase order or subcontract, we hold a formal kick-off meeting. Before any material is ordered, you and we sign off the Quality Assurance Plan that governs the whole job.
- Quality Assurance Plan (QAP) and Inspection and Test Plan (ITP) agreed and signed by both parties, with hold, witness and review points
- Named project manager and quality lead
- Submittal schedule, document register and transmittal procedure
- Pre-fabrication meeting to confirm tolerances, welding requirements and shipping sequence
You receive: Signed QAP and ITP, project schedule and document register
Drawing intake and fabrication planning
We fabricate to the shop drawings and details issued by your project team. We check what we receive for fabricability and raise questions before steel is cut.
- Intake of drawings, models and CNC data issued for fabrication
- Fabricability review, with RFIs sent back to your team and answers logged
- Cutting lists, nesting and a shop routing for each assembly
- Release to the shop only against the current approved revision, under revision control
You receive: Fabrication plan and RFI responses
Procurement and material control
Material is bought to the specified grades and tracked by heat number from receipt to dispatch.
- Mill test reports or EN 10204 3.1 certificates reviewed against the purchase order and grade
- Receiving inspection: dimensions, surface condition, marking and heat number
- Positive material identification (PMI) for alloy and stainless grades where specified
- Heat-number traceability carried through cutting, marking and fabrication
You receive: Material receiving reports and certificate pack
Welding procedure and welder qualification
No production welding starts until the welding procedures and the welders who will use them are qualified and approved. You receive the records for review.
- Welding Procedure Specifications (WPS) and Procedure Qualification Records (PQR) to AWS D1.1 or ASME Section IX
- Welder Performance Qualification (WPQ) for every welder, with continuity records
- European equivalent: WPS to EN ISO 15609-1, Welding Procedure Qualification Records (WPQR) to EN ISO 15614-1, and welder qualification to EN ISO 9606-1, under EN 1090-2 execution rules
- Qualification test coupons tested and witnessed by your inspector or a third party where specified
You receive: Approved WPS, PQR or WPQR, and welder qualification certificates
Fabrication
Cutting, fit-up and welding follow qualified procedures, with checks at each stage rather than only at the end.
- Production welding only by qualified welders, using the approved procedures
- Fit-up inspection before welding; preheat and interpass control where required
- Distortion control and dimensional checks against drawing tolerances
- Trial assembly of critical assemblies on request
You receive: Fit-up and welding records, dimensional reports
Inspection and testing
Inspection follows the agreed ITP. Your representative or a third-party inspector can attend any witness or hold point.
- Visual inspection of all welds; magnetic particle, penetrant, ultrasonic and radiographic testing to the specified extent and acceptance criteria
- Non-conformance reports (NCR) with root cause and corrective action, closed before release
- Verification of bolt holes and mating faces
- Final inspection and release note for each shipment lot
You receive: NDT reports, NCR log and inspection release
Shop-floor assembly and sub-assembly
Fabricated parts are brought together into sub-assemblies and assemblies on our shop floor, and checked for fit before they leave the factory.
- Shop-floor assembly of columns, beams, trusses and machine structures to the approved drawings
- Trial assembly of critical assemblies and match-marking of mating parts
- Dimensional checks of the assembled unit against drawing tolerances
- Bolt-hole, flange and mating-face verification
You receive: Assembly records and dimensional reports
Factory acceptance test (FAT)
Before the work is cleaned and coated, you or your representative witness the completed assembly in our factory and accept it against the agreed plan.
- FAT carried out to the agreed procedure in the signed QAP and ITP
- Visual and dimensional acceptance of assemblies, with fit-up and trial assembly shown where specified
- Functional checks on machines where the specification requires them
- Open points recorded and closed before release to surface preparation
You receive: Signed FAT report and release to surface preparation
Surface preparation
Surfaces are cleaned and prepared to the specified standard so the coating system will bond and last.
- Abrasive blast cleaning to the specified standard, for example SSPC-SP 10 or Sa 2.5
- Removal of weld spatter, sharp edges and surface defects
- Surface profile and cleanliness checks before any coating is applied
- Hold point: coating starts only after preparation is accepted
You receive: Surface preparation and profile records
Coating
Paint or galvanizing is applied to the specified system, with measurements recorded at each coat.
- Paint or galvanizing to the specified system and thickness
- Wet and dry film thickness readings, adhesion and holiday checks as required
- Cure time respected before handling and stacking
- Repair procedures for damage during handling and transport
You receive: Coating records and thickness reports
Packing and marking
Steel is packed for the transport route and marked so that it can be checked against the erection drawings on arrival.
- Piece marking and bundling in erection sequence
- Export packing and protection for sea freight in containers, flat racks or break-bulk
- Lifting points and securing arrangements for each package
- Packing list prepared for every lot
You receive: Packing lists and lot list
Shipping
Shipments leave only after final inspection and a complete document pack.
- Loading supervised and photographed
- Commercial invoices, certificates of origin and bills of lading issued to your logistics team
- Shipment tracking and delivery notices
- Release only after final inspection and the document pack are complete
You receive: Shipping documents and tracking
Delivery and site support
Your erector installs the steel. We stay available to your site team so that fit-up questions are answered quickly and corrections are made without delay.
- Shipment tracking and delivery notices
- Responses to site queries within agreed times
- Replacement or rework of any piece that does not fit or does not meet the specification
- Punch list tracking through to closure
You receive: Delivery records, query log and punch list
Closeout
The job is closed with a complete record set, delivered in the format you specify.
- As-fabricated records and final material list
- Quality data book: material certificates, welding and NDT records, coating and inspection reports
- Warranty terms and touch-up material where specified
- Closeout meeting and lessons-learned review
You receive: Quality data book and closeout report
Control points you can rely on
Quality is built into the sequence, so problems are caught where they are cheapest to fix.
- Quality Assurance Plan signed before material is ordered
- Approved drawings in hand before cutting
- Material certificates verified before release to the shop
- Welding procedures and welders qualified before production welding
- Factory acceptance test passed before coating
- Inspection signed off before coating and before shipping
- Documentation complete before closeout